Development of an integrated intelligent BIM-based model for multi-objective optimization in engineering assembly processes
Yanfen Zhang

TL;DR
This paper introduces a smart BIM-based model that optimizes construction assembly by balancing time, cost, and resource conflicts using advanced algorithms.
Contribution
The novel integration of BIM semantic modeling, MOPSO with dynamic weighting, and DQN-based reinforcement learning for multi-objective construction optimization.
Findings
The model achieves an average construction period of 85.2 days and budget cost of USD 1.486 million.
It outperforms existing methods in hypervolume (0.683), solution spread (0.227), and IGD (0.017).
The model shows robustness in handling complex trade-offs with fewer than 1.7 resource conflicts.
Abstract
To enhance construction efficiency and economic performance in prefabricated building projects under limited resource conditions, this study proposes an integrated intelligent optimization model based on Building Information Modeling (BIM) semantic representation. The model is designed to generate optimal assembly plans under multi-objective trade-offs, achieving a balanced compromise between shortened construction periods, reduced costs, and minimized resource conflicts. The study begins by constructing an assembly semantic model using the publicly available BuildingNet dataset, extracting key components’ geometric structures and spatial topology to establish a data foundation suitable for multi-objective scheduling modeling. A multi-objective particle swarm optimization (MOPSO) algorithm enhanced with a dynamic objective weighting mechanism is then introduced. By allowing flexible…
Genes, proteins, chemicals, diseases, species, mutations and cell lines named across the full text — each resolved to its canonical identifier and authoritative record.
Click any figure to enlarge with its caption.
Figure 1
Figure 2
Figure 3
Figure 4
Figure 5
Figure 6
Figure 7
Figure 8
Figure 9
Figure 10
Figure 11
Figure 12
Figure 13
Figure 14
Figure 15
Figure 16
Figure 17
Figure 18
Figure 19
Figure 20
Figure 21
Figure 22
Figure 23
Figure 24
Figure 25
Figure 26
Figure 27
Figure 28
Figure 29
Figure 30
Figure 31
Figure 32
Figure 33
Figure 34
Figure 35
Figure 36
Figure 37
Figure 38
Figure 39
Figure 40
Figure 41
Figure 42
Figure 43
Figure 44
Figure 45
Figure 46
Figure 47
Figure 48
Figure 49
Figure 50Peer Reviews
No public reviews on file for this paper yet. If you reviewed it on a platform where reviews are public (OpenReview, ICLR, NeurIPS, ICML), you can paste yours below so the community can read it here.
Videos
No videos yet. Explain this paper in a talk, walkthrough, or lecture? Add one.
Taxonomy
TopicsBIM and Construction Integration · Resource-Constrained Project Scheduling · Construction Project Management and Performance