Predicting the Impact of Scope Changes on Project Cost and Schedule Using Machine Learning Techniques
Soheila Sadeghi

TL;DR
This paper develops machine learning models to predict how scope changes affect project cost and schedule, aiding better project control and decision-making in dynamic project environments.
Contribution
It introduces predictive models using multiple machine learning techniques to estimate scope change impacts on project performance, highlighting key influential project attributes.
Findings
XGBoost achieved the best predictive accuracy.
Productivity rate and scope change magnitude are key predictors.
Models effectively identify potential cost and schedule deviations.
Abstract
In the dynamic landscape of project management, scope changes are an inevitable reality that can significantly impact project performance. These changes, whether initiated by stakeholders, external factors, or internal project dynamics, can lead to cost overruns and schedule delays. Accurately predicting the consequences of these changes is crucial for effective project control and informed decision-making. This study aims to develop predictive models to estimate the impact of scope changes on project cost and schedule using machine learning techniques. The research utilizes a comprehensive dataset containing detailed information on project tasks, including the Work Breakdown Structure (WBS), task type, productivity rate, estimated cost, actual cost, duration, task dependencies, scope change magnitude, and scope change timing. Multiple machine learning models are developed and evaluated…
Peer Reviews
No public reviews on file for this paper yet. If you reviewed it on a platform where reviews are public (OpenReview, ICLR, NeurIPS, ICML), you can paste yours below so the community can read it here.
Videos
No videos yet. Explain this paper in a talk, walkthrough, or lecture? Add one.
Taxonomy
TopicsBIM and Construction Integration · Manufacturing Process and Optimization
MethodsLinear Regression